The works are nearing completion at Durham UTC. Following a site visit BIMTS were pleased to see all the services were being fit nicely as designed in the BIM model.
March 15, 2017 | Uncategorised
The demolition works are now complete and the building is starting to take shape with the erection of the steelwork. BIMTS are pleased to see that the holes have all been pre-cut into the steelwork as requested following the coordination review of the 3D model.
March 25, 2016 | Projects
The design is now complete for Sunderland A&E. This was a new extension and renovation of the existing A&E department. The use of 3D modelling in Revit enabled us to pick up any coordination issues with the existing services/structure early on in the design...
March 18, 2016 | Projects
Projects (March 2016) BIM Technical Solutions are currently working with an International Emergency Lighting organisation in developing family components that are to be freely available on their web...